Implementation of Schedule
Activity
Phse - 1
4 x 100 TPD
Kilns
Phase - 1
Power Plant
15 MW
Phase - I
Coal Washery
Phase - II
4 x 100 TPD
PowerPlant
15 MW
Phase - III
Palletisation
Plant
Engineering
Aug 05 - Dec 05
Jan 06 - Jun 06
Jul 06 - Dec 06
Proposed
Construction
Jan 06 - Jul 06
Jul 06 - Dec 06
Jan 07 - Nov 07
Proposed
Supply & Equipment Erection
Apr 06 - Dec 06
Nov 06 - Jun 07
Aug 07 - Feb 08
Proposed
Commissioning
Complete in
July 05
Jan 07 - May 07
Jan 07-Dec 07
Mar 08
Proposed